Key facts
Lansing city workers are preparing to move into a new City Hall at 425 S. Grand Avenue, with a soft opening set for Monday, Nov. 23, and a grand opening and ribbon-cutting planned for 10 a.m. Monday, Nov. 301
Deputy Mayor Christopher Mumby said the city’s IT staff moved in first, giving them time to become familiar with the technology before other employees arrive1
A New Building for a New Era
The new City Hall is a $40 million, three-story building that replaced the previous 1950s-era headquarters2
The new building features a “one stop shop” on the first floor, bringing the treasury, clerk’s and assessor’s offices together1 2
The new City Council chambers are near the entrance rather than having to travel to the 10th floor.1 The chambers have space for roughly 155 people and can be rearranged for fairs, assemblies and other events1
Electronic monitors at the table for the mayor and council members display names and votes with thumbs-up or thumbs-down images1
Boji Group
The project was developed by the Boji Group and funded by a state appropriation.2 The project was completed on time and on budget2
The current City Hall, built in 1957, has experienced heating and cooling problems, pests, leaks and electrical issues1
City Hall will be closed Thursday and Friday while office equipment is moved, except for some district court trials, Mumby said1
A Building Named After a Former Mayor
Mumby adds the chamber will once again be named after former Mayor Tony Benavides1
The last steel beam for the new David C. Hollister City Hall was set into place Oct. 3, 2025.2 Hollister died on Sept. 22 of this year at the age of 842